An historical archive of the year of the great flood.


From the Mayor of Jamestown:

As we prepare to restore water service to the Town, PLEASE READ this important information.  We will need to have everyone’s participation during this process.

The current schedule* is:

 Activity Duration
 Construction of temporary water line from WTP to Mesa St 6/5 – 6/20
 Restoration of the Town’s water tanks 6/5 – 6/20
 Replacement of the WTP sand filters 6/5 -7/4
 Activation of the water lines on Mesa, Spruce, 16th, Pine, Porphyry, Gillespie 6/30
 Construction of the water line and Ward St 6/20-7/3
 Activation of the water line on Ward St 7/3
 Construction of the water line and Main St (Ward to JVFD) 6/25-7/18
 Activation of the water line on Main St (Ward to JVFD) 7/19
 Construction of the water line on High St and 15th St 7/20-8/3
 Activation of the water line on High St and 15th St 8/4
 Construction of the water line on Lower Main St and 12th 7/20-8/4
 Activation of the water line on Lower Main St and 12th 8/4
 Construction of Ward St Box Culvert 6/30 – 7/17
 Construction of Gillespie Gulch Culvert (being redesigned) 7/26 – 7/29
 Construction of permanent water line from WTP to Mesa St 8/6 – 8/8

* Please note this schedule is subject to change.

Duran Excavating, the Town’s water distribution system contract, will notify property owners within 7 days of work starting on the water lines near your house.  This will include the dates scheduled for flushing and activation of the water main and service line for your property. You will be responsible for flushing and activating the plumbing inside your house.

Printed copies of the attached notice are available at the Town Hall.

Please contact me or the Town Hall (303-449-1806) if you have any questions.

Sincerely,
Tara